The FT says Anthropic bought 1.7 gigawatts of gas-generator commitments for about $3.4 billion
Martha Muir’s Sunday report, citing a person familiar with the matter, says a late-September deal with San Antonio’s OnePWR included installation work and did not include the company or its staff. Reuters said it could not immediately verify that account. Piper Sandler’s September page records a $3.4 billion sale of a power platform to an unnamed frontier lab.
Deep dive3 minIn-depth
Priya Shah3 min read
- Anthropic
- Data centers
- Power
- OnePWR

Photo: Financial TimesSource page
The Financial Times reported on Sunday that Anthropic bought commitments for 1.7 gigawatts of heavy-duty gas-fired generators for about $3.4 billion. Martha Muir’s story is headlined “Anthropic strikes $3.4bn deal to generate gas-fired power for data centres,” with the deck that the lab is bypassing traditional suppliers for scarce equipment as demand for energy surges. Reuters, in a dispatch CNBC published at 8:50 a.m. EST and The Economic Times carried with a last update of 4:59 p.m. IST, said it could not immediately verify the report. CNBC said Anthropic and OnePWR did not respond to requests for comment.
The Reuters account, citing a person familiar with the matter, places the purchase in late September. The counterparty is OnePWR Solutions, an equipment supplier based in San Antonio, Texas. Anthropic did not acquire OnePWR, and none of the supplier’s employees transferred. The deal did include the engineering and construction capability needed to install the generators. That is the outline Reuters printed. It does not name a manufacturer.
Caterpillar, in the second-day accounts
Wolfie Zhao at TheEnergyMag, citing the FT, writes that Anthropic took over OnePWR’s orders for Caterpillar generators, and that the lab had first planned to buy electricity from OnePWR. Ryan Gibson at WebProNews, also writing Sunday, attributes a more specific version of that detail to Investing.com’s summary of the FT report: OnePWR had ordered the generators from Caterpillar about two years ago, needed financing to complete the purchase, and Anthropic moved from prospective customer to holder of the equipment orders. Gibson does not quote a Caterpillar sentence from the newspaper itself. Reuters’ rewrite does not mention Caterpillar at all.
What the bank’s page actually says
Piper Sandler’s transaction page for OnePWR Solutions, which it also lists as CK Holdings Group, LLC, marks a sell-side assignment “09/26” at “$3.4 Billion.” The sentence on the page says the firm “served as exclusive financial advisor for OnePwr on its sale of its power generation platform to a frontier AI lab.” The page does not name Anthropic. It does not mention Caterpillar, gas, or a gigawatt figure. The seller, the month and the rounded price match the newspaper account. They do not, on their own, identify the buyer or describe the machines.
Gibson writes that the FT called the transaction the largest known single purchase of power-generation equipment by an AI lab. That is the paper’s characterization, as he relays it. Anthropic has not published a ranking of its own.
What was already in the 2 November prospectus
The amended registration statement Anthropic filed on 2 November already said some planned sites depend on gas burned on the property. Gibson quotes the filing:
Certain of our planned data center facilities rely on dedicated on-site natural gas-fired generation, which exposes us to fuel price volatility and supply disruptions that are outside of our control.
— Anthropic Form S-1/A, filed Nov 2, 2026, as quoted by Ryan Gibson, WebProNews
The same account of the filing says turbines and generators are among equipment that has faced extended delivery timelines, price increases and allocation constraints, and that some infrastructure has to be ordered years ahead, with large payments before delivery. Anthropic also said it generally bears fuel costs on a pass-through basis, without cost caps. Gibson, recounting that amendment, puts purchase commitments at about $895.4 billion, substantially all of it for compute and infrastructure, with roughly $447.5 billion expected before the end of 2030. Those are disclosed commitments. They are not a price tag for the OnePWR generators.
What Sunday’s accounts do not show
Reuters does not give the sites where the generators would be installed, a delivery schedule, or how the $3.4 billion divides between equipment and installation. A commitment to buy machines another company had ordered is not a plant that is running, and it is not a fuel contract. The FT report, the Reuters rewrite and the Piper card do not show a generator installed or a permit issued. They show a reported purchase of equipment orders, a bank record of a platform sale to an unnamed frontier lab, and a prospectus that had already said some planned facilities depend on gas.