Microsoft leaves Nscale’s Loughton data centre after the power date slips into the 2030s
Reuters on Monday: Microsoft has ended its agreement to anchor Nscale’s site in Loughton, Essex, after grid officials told the company not to expect a connection until the 2030s. The plan was 23,040 Nvidia GB300 chips and 50 megawatts for Azure, with operations early next year. Microsoft says the decision is one site. Nscale says it will look for other power, and that the rest of the Microsoft relationship stands. The BBC puts the project at £2 billion and 250 jobs.
Feature3 minEasy
Priya Shah3 min read
- Microsoft
- Nscale
- Data centres
- UK
- Nvidia

Photo: Chris Holifield / Geograph Britain and Ireland, via Wikimedia CommonsCC BY-SA 2.0
Microsoft has pulled out of the deal to anchor Nscale’s data centre in Loughton, Essex, after the expected power connection moved into the 2030s. Paul Sandle at Reuters reported the withdrawal on Monday. A Microsoft spokesperson said the company remains committed to its partnership with Nscale, including work on digital infrastructure and AI growth, and then drew the boundary: “This decision relates to a single site.” The site is the one where, Reuters wrote, electricity grid officials had told Nscale they did not expect to supply power until the 2030s. Reuters said the Telegraph reported Microsoft’s move first.
Our relationship with Microsoft remains strong and long-term, and this unfortunate London-wide grid issue has no impact on our other contracts.
— Nscale spokesperson, to Reuters, 19 October 2026
The same spokesperson said Nscale is still committed to Loughton and to the UK, and that it is exploring alternative power for the site and other expansion sites in Britain. The BBC’s account, by Alice Cunningham, has Nscale on the same two points — other power, and a Microsoft relationship that still covers projects in Norway, Portugal and the United States — and says Microsoft declined to comment. Reuters has the spokesperson’s sentence. The BBC also reports that Nscale pledged £2 billion to the Loughton centre, that the site is expected to mean 250 permanent jobs when it opens, and that only last month Microsoft had said some of a $30 billion (£22 billion) UK investment would fund the supercomputer there.
Early next year was the old date
Reuters’ specification of the project, attributed to what the companies said last year, is 23,040 Nvidia GB300 GPUs, 50 megawatts, and a start early next year, supplying AI computing for Microsoft Azure in Britain. The Wall Street Journal, in Mauro Orru’s account on Monday, describes the same facility as a 50-megawatt lease with about 23,000 GB300 chips, bought by Nscale as its first UK data centre, and expected to go live by the end of this year before the grid delay. The BBC says the power supply itself had been due at the end of this year, and that the Telegraph reported on Sunday that it will not arrive until the 2030s. The Monday news is the tenant. The date had already slipped.
Dan Milmo at The Guardian reported on 24 September that the Loughton project, described when it was announced as the country’s largest AI supercomputer, would miss a launch next year and could be held into the mid-2030s. He also noted that the Guardian had reported in March that the planned location was still an operational scaffolding yard. The site was one of the technology deals announced during President Donald Trump’s visit to Britain in September 2025. Reuters’ Monday story puts the wider constraint in one figure: bottlenecks in grid-connection queues are delaying data centre projects by as long as 13 years.
Nscale filed for a US initial public offering last month. Reuters, citing the prospectus, said Microsoft and Anthropic were expected to be among its major customers. The company sells computing capacity, power, data centres and software for training and running models. Reuters says its total contracted value has gone from $100 million to more than $103 billion in two and a half years, and names CoreWeave, Nebius, Crusoe and Lambda as the companies it competes with. Monday’s statement does not cancel that book. It takes Microsoft off one site whose power date is no longer the one the lease assumed, and leaves Nscale looking for a different way to feed Loughton.